Skip to main content

Author: TNTP LAW

Key considerations when entering into a mortgage contract

Lending activities always carry numerous risks due to various reasons, such as borrowers failing to repay, repaying incompletely or late, or losing the ability to pay. To mitigate these risks, lenders often require borrowers to implement security measures such as pledges, mortgages, or third-party guarantees. Among these measures, mortgage is a commonly chosen option by lenders. To implement this measure, the parties must enter into a mortgage contract. In this article, TNTP will outline the key points that parties need to consider when entering into a mortgage contract.

1. Form of the mortgage contract

Article 319.1 of the 2015 Civil Code stipulates that “The mortgage contract takes effect from the time of conclusion, unless otherwise agreed or otherwise provided by law.” Thus, the above regulation implicitly confirms that the mortgage is only recognized if the parties enter into a mortgage contract. If the obligor fails to perform or improperly performs their obligations, the mortgagee has the right to handle the mortgaged asset.

In practice, the content regarding asset mortgage can be separately documented (commonly known as a mortgage contract) or recorded as clauses within the main contract (loan contract). However, for certain types of mortgaged assets, the law requires that the mortgage document be notarized, authenticated, and registered as a secured transaction, so parties usually prioritize creating a mortgage contract. For example, mortgage contracts for land use rights and assets attached to land must be notarized or authenticated.

2. Content of the mortgage contract

Law does not stipulate mandatory contents for a mortgage contract. Therefore, the parties will specify terms suitable to their circumstances and actual conditions. Basic terms that should be included in a mortgage contract are:

• Information of the mortgagor and mortgagee;
• Information on the mortgaged asset, such as type, quantity, and value;
• Information on the loan under the asset loan contract secured by the mortgagor;
• Rights and obligations of the parties;
• Liability for contract breaches;
• Dispute resolution methods;
• Mortgaged asset realisation;
• Cases of contract termination and legal consequences;
• Contract validity, etc.

3. Effectiveness of the mortgage contract and its effectiveness against third parties

Based on Article 319.1 of the 2015 Civil Code and Article 22 of Decree 21/2021/ND-CP, the mortgage contract takes effect from the time of conclusion, unless otherwise agreed or law stipulates otherwise, such as provisions on notarization and authentication. The ineffectiveness of the mortgage against third parties does not alter or terminate the validity of the mortgage contract.

Accordingly, the mortgage measure only takes effect against third parties if the mortgage contract has legal effect. The time of effectiveness against third parties is the time of registration. Decree 99/2022/ND-CP stipulates cases that must be registered and cases registered upon request. Cases that require registration include mortgage of land use rights, mortgage of residential houses, and assets attached to land in cases where ownership rights are certified on the Certificate of ownership, mortgage of aircraft, mortgage of ships, etc. For other types of assets, the parties have the right to agree on whether to register the mortgage measure.

The mortgage contract will cease to be effective upon the occurrence of events such as (i) The obligation secured by the mortgage terminates; (ii) The mortgage is canceled or replaced by another security measure; (iii) The mortgaged asset has been realized; and (iv) Other cases as agreed by the parties.

The above article on “Key considerations when entering into a mortgage contract” is presented by TNTP. Should readers have any issues to discuss with TNTP, please contact us for timely support.

Best regards,

CASE LAW NO. 23/2018/AL REGARDING THE VALIDITY OF LIFE INSURANCE CONTRACT WHEN THE INSURANCE BUYER FAILS TO PAY INSURANCE PREMIUMS DUE TO THE FAULT OF THE INSURANCE COMPANY

Life insurance is a product of insurance companies, established through life insurance contracts with clear benefits and terms to protect participants from health events or physical and life risks. Therefore, many people have been purchasing life insurance in various periodic payment forms. In practice, there are many cases where customers stop paying premiums, affecting the validity of the life insurance contract. Typically, the customer’s failure to pay the premium is the customer’s obligation fault in fulfilling the contract. However, in practice, there are cases where the customer does not pay the premium due to the fault of the insurance company. Case Law No. 23/2018/AL is a typical case of this issue. In this article, TNTP will further clarify the court’s assessment of this case.

1. Summary of the case

a) The plaintiff – Mrs. Pham Thi T presented:

Her husband, Mr. Tran Huu L, had registered to purchase life insurance from P Life Insurance Company Limited. Her husband was involved in a fatal accident. According to the contract, she is the beneficiary. Now, she is requesting the defendant to pay the insurance amount of 300 million VND and interest at the basic interest rate from August 2005 until now, which is 126 million VND, for a total of 426 million VND.

b) The defendant, P Life Insurance Company Limited, represented by Mr. Nguyen Quoc T, presented:

Mr. L was required to pay the second insurance premium on June 24, 2005, but after being granted a 2-month extension, he still did not pay the premium. Mr. L passed away on August 27, 2005, which was 3 days after the insurance contract had become invalid. Therefore, the defendant does not accept to pay the amount requested by the plaintiff.

c) The party with related rights and obligations, Ms. Vu Thi Minh N, presented:

She is the agent of the defendant and had sold the insurance to Mr. L. She had an agreement with Mr. L that she would directly collect the insurance premiums at his house when they were due. However, when the final premium was due, she had to attend a political study session in the province, so she was unable to collect the premium. The failure to pay the premium was due to objective circumstances, so she requests that the defendant pay the insurance amount to the plaintiff.

d) In the first instance civil judgment No. 38/2008/DS-ST dated August 21, 2008 of the People’s Court of District 1, Ho Chi Minh City, it was decided:

• Dismiss the request of Mrs. Pham Thi T to demand that P Life Insurance Company Limited pay the insurance amount and interest for late payment of 426.000.000 VND.
• Regarding the court fees: Mrs. Pham Thi T must bear the first instance civil court fees of 7.890.000 VND, but the 6.000.000 VND prepaid court fees according to the payment receipt No. 2185 dated June 9, 2006 of the Ho Chi Minh City Civil Judgment Enforcement Agency will be deducted. Mrs. T must still pay 1.890.000 VND.

e) On September 1, 2008, Mrs. Pham Thi T appealed.

f) At the appellate hearing:

• The plaintiff did not withdraw the lawsuit and the appeal request.
• The parties failed to reach an agreement on the resolution of the lawsuit.
• Ms. T presented the appeal request, asking the Trial Panel to accept her request to require P Life Insurance Company Limited to pay the insurance amount and interest for late payment of 426.000.000 VND. The reason is that the company’s representatives did not come to collect the insurance premium, not because she did not pay. The lawyer defending Ms. T’s legitimate rights and interests requested the Trial Panel to accept this request of Ms. T.
• Mr. Nguyen Quoc T, the representative of P Life Insurance Company Limited, along with the lawyer defending the company’s legitimate rights and interests, requested the Trial Panel to uphold the first instance judgment.

2. Assessment of the Court

• The appeal filed by Ms. Pham Thi T was made within the statutory time limit and is valid.

• Content of Case law: Based on the life insurance application dossier (pages 15-17), the address for P Life Insurance Company Limited to collect the premiums is at house number 231, Hamlet 3, B commune, G district, Ben Tre province, which is the house of Mr. L. This is also consistent with the testimony of Ms. N, who is the insurance agent and premium collector for P Life Insurance Company Limited.

• Considering the appeal request of Mrs. T, she reasons that Mr. L did not pay the insurance premiums on time because the company did not send the collector to collect the payments. This argument has its ground as evidenced by the information provided above.

• Based on the certificate of confirmation from the B commune police, it shows that Mr. L passed away on August 27, 2005 due to an accidental fall and head injury that led to his death.

• Content of Case law: Considering that Mr. L had signed an insurance contract through a life insurance application dossier with a coverage of 300.000.000 VND, and the fact that he had not paid the 2nd premium installment, as analyzed above, was not due to his fault, therefore, the appeal request of Mrs. T, requiring P Life Insurance Company Limited to pay the insurance benefit when Mr. L passed away due to an accident, has a basis to be accepted.

• Content of Case law: Considering the request of the representative of P Life Insurance Company Limited, who claimed that Mr. L did not pay the 2nd premium installment by the due date of August 24, 2005, and Mr. L passed away on August 27, 2005, thus his insurance contract had expired, this argument has no basis. As analyzed above, the reason why Mr. L did not pay the premium was because the company did not send the collector to collect the premium. This is also clearly stated on page 5 of the information for customers booklet, which mentions that premium collection at the customer’s home includes quarterly, semi-annual, or annual collection, or at an address with 2 or more contracts, which is consistent with the fact that Mr. L had signed 3 contracts with P Life Insurance Company Limited for himself, Mrs. T, and Ms. H. Therefore, the Trial Panel does not accept the request of the representative of P Life Insurance Company Limited, nor the proposal of the lawyer defending the legitimate rights and interests of P Life Insurance Company Limited.

• Considering the request of Mrs. T to require P Life Insurance Company Limited to pay interest on the late payment from August 27, 2005 until the date of the court trial, this request has no basis. Because the insurance certificate issued by P Life Insurance Company Limited to Mr. L did not state any terms about interest rates, therefore the Trial Panel does not accept this request from Mrs. T.

• Therefore, the Trial Panel partially accepts Mrs. T’s appeal request, revising the first-instance judgment to require P Life Insurance Company Limited to pay the insurance benefit of 300.000.000 VND according to the contract for Mr. L’s accidental death, with Mrs. T as the beneficiary.

3. Comment on Case law

• Based on Clause 2, Article 23 of the Insurance Business Law 2000 (as amended and supplemented in 2010) on termination of insurance contracts stipulated a situation that the insurance contract can be terminated: “The insurance purchaser does not pay the full insurance premium or does not pay the premium within the time limit agreed upon in the insurance contract, unless the parties have agreed otherwise.”

Applying this regulation to the case, the parties had a different agreement regarding the payment of the insurance premium, based on the confirmed evidence that Mr. L would pay the premium at home when the P Company staff came to collect the premium. Therefore, the fault here does not lie with Mr. L. Thus, the requirement for P Company to pay the insurance benefit when Mr. L passed away due to an accident is well-grounded and should be accepted.

• Regarding P Company’s claim that Mr. L’s insurance contract had expired, this claim has no basis. The reason Mr. L did not pay the insurance premium was because the company staff did not come to collect the premium. This is also clearly stated on the information for customers booklet, which states that premium collection at home includes quarterly, semi-annual, or annual collection, or from an address with 2 or more contracts, and since Mr. L had signed 3 insurance contracts with P Life Insurance Company Limited for himself, Mrs. T, and Mrs. H, the insurance company must send a collector to his house to collect the premiums. Therefore, the Trial Panel’s decision to not accept the request of the representative of Company P, nor the proposal of the lawyer defending the legitimate interests of Company P, is well-founded.

Above is TNTP’s article on “Case law No. 23/2018/AL regarding the validity of life insurance contract when the insurance buyer fails to pay the insurance premiums due to the fault of the insurance company“. We hope this article will be helpful to our readers.

Best regards,

Is the company allowed to deduct employees’ wages?

In the context of Vietnam’s economy, deducting employees’ wages is a contentious issue, especially when considering its legality and fairness. However, the question remains whether wage deduction is a reasonable and fair method for both parties. In this article, TNTP will present the points that both businesses and employees need to be aware of regarding the deduction of employee wages.

1. Cases where the company can deduct wages:

• According to Article 124 of the Labor Code 2019, disciplinary measures for employees include reprimand, deferment of a pay raise for up to 6 months, demotion, and dismissal.

• Additionally, under Clause 2 Article 127 of the Labor Code 2019, it is prohibited for employers to apply monetary fines or reduce the employee’s wage.

Thus, although companies, as employers, can use disciplinary measures to manage personnel and maintain discipline within the company, withholding wages instead of applying disciplinary measures is prohibited. Therefore, companies are not allowed to deduct employees’ wages for disciplinary purposes.

• However, in practice, there are cases where companies or employers arbitrarily deduct employees’ wages. According to Article 102 of the Labor Code 2019, employers are only allowed to deduct employees’ wages in the following cases:

– When the employee damages tools, or equipment, or causes damage to the company’s property.

– When the employee loses tools, equipment, or other property entrusted by the employer.

– When the employee consumes materials exceeding the allowable limit, they must compensate for the damage either partially or entirely based on market prices or internal labor regulations.

Thus, the company is only allowed to deduct employees’ wages to compensate for damage caused to tools, equipment, or company property, or for excessive consumption of materials beyond the permitted limit.

2. Regulations on deducting employees’ wages

According to Article 102 and Article 129 of the Labor Code 2019, deducting employees’ wages to compensate for damages must also adhere to the following regulations:

• Amount of compensation for damages

– In case the damage caused by an employee is not serious, not deliberate, and is worth less than 10 months’ region-based minimum wage announced by the Government, the employee shall have to pay a compensation of not more than his/her 03 months’ salary, which shall be monthly deducted from his/her salary. Any monthly deduction shall not exceed 30% of the net monthly salary of the employee, after the deduction of insurance premiums.

– In cases where materials are consumed beyond the permitted limit, the employee shall pay compensation for damage in full or in part at the market price or as stipulated in the internal labor regulations or the responsibility contract (if any).

– In case this is caused by a natural disaster, fire, war, major epidemic, calamity, or another force majeure event that is unforeseeable and insurmountable, and all necessary measures and possibilities for avoidance have been taken, the compensation shall be exempted.

• Notification of reasons for wage deductions: Employees have the right to know the reasons for the deduction of their wages, and the deduction must be communicated transparently.

3. Handling violations in cases where the company deducts employees’ wages against legal regulations

• According to Clause 3, Article 19 of Decree 12/2022/NĐ-CP, apart from the cases permitted to deduct wages as mentioned in section 1, companies engaging in arbitrary deduction of employees’ wages may face administrative penalties ranging from 20,000,000 VND to 40,000,000 VND. Employers using fines or wage cuts instead of applying labor disciplinary measures may face these penalties.

• Additionally, according to Clause 4, Article 19 of Decree 12/2022/NĐ-CP, measures to remedy the consequences of wage cuts instead of labor disciplinary measures include compelling the employer to return collected amounts or pay full salaries to employees.

4. Solutions for companies

• Enhance legal awareness: Companies and employees need to be trained on legal regulations related to wage deductions and labor discipline to avoid violations and protect rights.

• Implement fair procedures: Procedures for handling discipline and wage deductions should be fair, transparent, and consistent, ensuring that employees have the opportunity to explain and protect their rights.

• Seek legal advice from lawyers or legal experts: Companies and employees should seek support from lawyers or legal experts to advise and assist with legal issues related to labor. Lawyers or legal experts can help companies assess and manage legal risks, ensuring compliance with legal regulations.

Companies must strictly adhere to legal regulations regarding wage deductions to protect employees’ rights and maintain a fair and transparent working environment. Applying effective and transparent disciplinary measures, along with creating a positive work environment and consulting legal experts, will help companies develop sustainably and build trust among employees.

The above article, ” Is the company allowed to deduct employees’ wages?” is presented by TNTP for our valued readers. If you have any issues for discussion, please contact TNTP for assistance.

Best regards,

CASE LAW NO.36/2020/AL REGARDING THE VALIDITY OF MORTGAGE CONTRACTS FOR LAND USE RIGHTS WHEN THE LAND USE RIGHTS CERTIFICATE IS REVOKED, CANCELLED

The land use rights mortgage contract is one of the most common methods that the borrower chooses to mortgage their land use rights as collateral to borrow credit from the bank. In practice, there are many disputes arising from the non-performance of the borrower with the bank for a long time, leading to the bank initiating a lawsuit against the borrower to the Court for resolution. However, during the period when the mortgage contract is valid, the borrower’s Land use rights certificate is revoked or cancelled. Similar events occur quite often in practice and Caselaw No. 36/2020/AL is a typical example for the Court to apply in practice when adjudicating cases with similar content. In this article, TNTP’s lawyers will comment and clarify the content of Caselaw No. 36/2020/AL.

1. Summary of the case

a) On March 22, 2010, Bank V entered into Credit Contract No. 10.36.0015 with Mr. Nguyen Van C and Mrs. Vu Thi T. Accordingly, Bank V lent Mr. C and Mrs. T 900.000.000 VND, with an annual interest rate of 12% within the term; the overdue interest rate is 150% of the in-term interest rate; the loan term is 12 months.

In order to secure the loan, Mr. C and Mrs. T have mortgaged their asset, which is the land use rights of a parcel with an area of 3.989,7 m2 belonging to parcel No. 12, map sheet No. 05, H Commune, B Town (Land use rights certificate No. Đ544493 issued by the People’s Committee of B Town on July 14, 2004) under Mortgage Contract No. 10.36.0015 dated March 18, 2010. The secured transaction was registered at the Land use rights Registration Office of B town on March 19, 2010.

b) After borrowing the money, Mr. C and Mrs. T did not fulfill their payment obligations to Bank V. Therefore, Bank V filed a lawsuit demanding that Mr. C and Mrs. T repay the entire debt of VND 1.449.537.500 (of which VND 900.000.000 is the principal and VND 549.537.500 is the temporary interest calculated as of July 17, 2013 and interest until the date of debt repayment).

c) During the time the Mortgage Contract was in effect, the People’s Committee of B town issued Decision No. 3063/QĐ-UBND dated August 31, 2011 to revoke Land use rights certificate No. Đ544493. However, Bank V determined that although Land use rights certificate No. Đ544493 no longer exists, the land use right of the 2,400 m2 area that Mr. C and Mrs. T had previously transferred (after being adjusted according to the actual situation) has been completed, so it still has collateral value for the loan of Mr. C and Mrs. T. Bank V will request the Civil judgment enforcement Agency of B city to prioritize the auction of the collateral asset to Bank V.

d) The defendant, Mr. Nguyen Van C, stated that he confirmed the information about the Credit Contract and Mortgage Contract as presented by Bank V is correct. After borrowing, he paid Bank V a portion of the interest debt, which is 122.775.000 VND, but he has not paid the principal amount, and he agrees with Bank V’s lawsuit request.

e) Mr. C and Mrs. T had filed an administrative lawsuit against Decision No. 3063/QĐ-UBND dated August 31, 2011 of the People’s Committee of B Town. However, both the court of first instance and the court of appeals did not accept their request, so he requested the Court to resolve the case according to the provisions of the law, as the collateral asset no longer exists.

f) In the First Instance Commercial Judgment No. 04/2013/KDTM-ST dated December 10, 2013, the People’s Court of Ba Ria – Vung Tau province decided:

• Mr. Nguyen Van C and Mrs. Vu Thi T are required to pay Joint Stock Commercial Bank V – B Branch the amount of VND 1.449.537.500, of which VND 900.000.000 is the principal and VND 549.537.500 is the interest.

• The Mortgage Contract No. 10.36.0015 dated March 18, 2010 signed between Joint Stock Commercial Bank V – B Branch and Mr. Nguyen Van C and Mrs. Vu Thi T regarding the mortgage of a land area of 3,989.7 m2 belonging to parcel No. 12, map sheet No. 05, H Commune, B Town, as per Land use rights certificate No. D544493 issued by the People’s Committee of B Town (now the People’s Committee of B City) on July 14, 2004 in the names of Mr. Nguyen Van C and Mrs. Vu Thi T, is declared void. Therefore, it has no collateral value for the repayment of the debt under Credit Contract No. 10.36.0015 dated March 3, 2010.

g) On December 23, 2013, Joint Stock Commercial Bank V – B Branch filed an appeal.

h) In the Appellate Commercial Judgment No. 48/2014/KDTM-PT dated August 15, 2014, the Appeals Court of the People’s High Court in Ho Chi Minh City decided:

• Dismiss the appeal request of Joint Stock Commercial Bank V – B Branch; to uphold the First Instance Commercial Judgment No. 04/2013/KDTM-ST dated December 10, 2013 of the People’s Court of Ba Ria-Vung Tau province.

• To accept the request of Joint Stock Commercial Bank V – B Branch regarding the dispute over the credit contract against Mr. Nguyen Van C and Mrs. Vu Thi T.

– To order Mr. Nguyen Van C and Mrs. Vu Thi T to pay Joint Stock Commercial Bank V – B Branch the amount of VND 1.449.573.500, of which the principal is 900.000.000 VND and the interest is 549.573.500 VND.

– To declare the Mortgage Contract No. 10.36.0015 dated March 18, 2010 signed between Joint Stock Commercial Bank V – B Branch and Mr. Nguyen Van C and Mrs. Vu Thi T regarding the mortgage of an area of 3,989.7m2 belonging to parcel No. 12, map sheet No. 5, H Commune, B Town according to the Land use rights certification No. D544493 issued by the People’s Committee of B Town (now B City) on July 7, 2004 in the name of Mr. Nguyen Van C and Mrs. Vu Thi T is invalidated. It has no value to secure the payment of the debt for the credit contract No. 10.36.0015 dated March 22, 2010.

i) After the appellate trial, Joint Stock Commercial Bank V submitted a petition requesting a review under the cassation procedure for the above-mentioned appellate judgment.

j) On August 15, 2014, the Chief Justice of the People’s Supreme Court filed a cassation appeal against the Commercial Appellate Judgment No. 48/2014/KDTM-PT of the Appellate Court of the People’s High Court in Ho Chi Minh City regarding the part declaring the Mortgage Contract No. 10.36.0015 dated March 18, 2010 invalidated; requesting the Judicial Council of the People’s Supreme Court to hear the cassation and vacate a part of the above-mentioned Commercial Appellate Judgment and vacate a part of the Commercial First Instance Judgment No. 04/2013/KDTM-ST dated December 10, 2013 of the People’s Court of Ba Ria – Vung Tau Province regarding the part declaring the Mortgage Contract No. 10.36.0015 dated March 18, 2010 invalid; returning the case file to the People’s Court of Ba Ria – Vung Tau Province to re-trial at the first instance in accordance with the provisions of law.

k) At the cassation trial, the representative of the People’s Supreme Procuracy proposed that the Judicial Council of the People’s Supreme Court accept the Cassation Appeal of the Chief Justice of the People’s Supreme Court.

2. Assessment of the Court

• Bank V and Mr. Nguyen Van C both confirmed that Bank V and Mr. Nguyen Van C, Mrs. Vu Thi T signed Credit Contract No. 10.36.0015 dated March 22, 2010 and Mortgage Contract No. 10.36.0015 dated March 18, 2010. The mortgaged asset is a land area of 3,989.7 m2 belonging to parcel No. 12, map sheet No. 05, H Commune, B Town, according to Land use rights certificate No. Đ544493 issued by the People’s Committee of B Town on July 14, 2004 in the name of Mr. Nguyen Van C and Mrs. Vu Thi T. The asset was registered for secured transactions at the Land use rights Registration Office of B Town on March 19, 2010. According to the provisions of Article 343 of the Civil Code 2005; Point c, Clause 1, Article 10 and Point a, Clause 1, Article 12 of Decree No. 163/2006/NĐ-CP dated December 29, 2006 of the Government on secured transactions, the mortgaging of the above land use rights is in accordance with the provisions of law.

• Main point of Case law: On August 31, 2011, the People’s Committee of B Town issued Decision No. 3063/QĐ-UBND on the revocation and cancellation of the Land use rights certificate No. Đ544493 issued by the People’s Committee of B Town on July 14, 2004 in the name of Mr. Nguyen Van C and Mrs. Vu Thi T. The revocation and cancellation of the aforementioned Land use rights certificate was due to errors in the land area and the order and procedures for issuing the Land use rights certificate to Mr. C and Mrs. T. However, the revocation and cancellation of the Land use rights did not deprive the lawful land use rights of Mr. C and Mrs. T, as the transfer of land use rights between the couple Mrs. Tran Thi Ngoc H, Mr. Tran Huynh L and the couple Mr. C, Mrs. T had been completed, and the parties had no disputes over this transfer contract.

On the other hand, before the Land use rights certificate of Mr. C and Mrs. T was revoked, Mr. C and Mrs. T had mortgaged this land use right to the Bank multiple times to borrow money, most recently on March 19, 2010. The land use rights mortgage contract between Mr. C, Mrs. T and the Bank complied with the provisions of the law, so this contract is legally valid. The court of first instance and the court of appeal based on Article 411 of the Civil Code 2005 stated that the land use rights mortgage contract No. 10.36.0015 dated March 18, 2010 mentioned above is invalid because the object of this mortgage contract no longer exists is not appropriate.

• According to Official Letter No. 887/CNVPĐK-ĐKCG dated March 28, 2017, the Branch of the Land Registration Office of B City determined that: After the People’s Committee of B Town issued Decision No. 3063/QĐ-UBND on the revocation and cancellation of the Land use rights certificate No. Đ544493 and the Administrative Judgment No. 01/2013/HC-PT dated January 4, 2013 of the People’s Court of Ba Ria – Vung Tau Province took effect, the Civil Judgement Enforcement Agency of B City had issued Decisions on Judgment Enforcement in accordance with the effective civil judgments that Ms. Tran Thi Ngoc H had the obligation to enforce. Accordingly, the property of 2.741,1 m2 of land in parcel 386, map sheet No. 05, H Commune was organized for auction. Mr. Bui Van C1 was the successful bidder for the land use rights of 2.747,1 m2 of land. On March 14, 2016, the People’s Committee of B City issued the Land use rights certificate No. CA959055 for the auctioned area to Mr. Bui Van C1.

• Therefore, to ensure the rights and obligations of the parties involved, when re-adjudicating the case, the court of first instance needs to rely on Clause 4, Article 68 of the Civil Procedure Code to bring in the Civil judgment enforcement Agency of B City, Ms. Tran Thi Ngoc H, Mr. Bui Van C1, and the People’s Committee of B City as parties with related rights and obligations, in order to comprehensively and thoroughly resolve the case.

3. Comment on Case law

• Regarding the subject matter of a Mortgage Contract:
– According to the regulations in the Land Law 2013, in order to be able to mortgage the land use rights (“LUR”), the following 4 conditions must be fully satisfied:
(i) The land to be mortgaged must have a Land use rights certificate;
(ii) The land must not be in dispute;
(iii) The LUR must not be seized for the enforcement of a judgment;
(iv) The land must still have a remaining term of use, and only the LUR within the remaining term of use can be mortgaged.
– According to the definitions in the Land Law 2003 and the Land Law 2013, the Land use rights certificate is a legal document by which the State confirms the LUR of the person who has the LUR (Clause 20 Article 4 of the Land Law 2003 and Clause 16 Article 3 of the Land Law 2013). The issuance of a Land use rights certificate occurs when the land user has already had the LUR, and it is only applied to those entities that have the LUR. This also means that in practice, there will be entities that have the LUR but have not yet been issued a Land use rights certificate.

Thus, in essence, it is not that the entity only has the LUR after being issued a Land use rights certificate. The LUR of the entity may have arisen before the entity was issued a Land use rights certificate.

– According to the content recorded in the Case law, LUR is the subject matter of the mortgage relationship. The important issue is to determine whether the mortgagor still has the LUR and the remaining LUR after the Land use rights certificate is revoked. The conclusion of the cassation review has affirmed that “… The revocation, cancellation of the Land use rights certificate does not deprive the legitimate of the transferred land use rights” (of the mortgagor). The consequence of this only occurs when the revocation, or cancellation of the Land use rights certificate “is due to errors in the land area and the order and procedures for issuing the Land use rights certificate”. Furthermore, the mortgagor’s LUR in this case still exists. Specifically, the Case law has clearly stated that the transaction “has been completed, and the parties have no disputes about this transfer contract”. When the LUR transfer contract is not deemed invalid, the LUR of the transferee (the mortgagor) is still recognized.

Accordingly, the above is the basis for the Case law to affirm that the land use rights (LUR) of the mortgagor “are not lost”.

• Regarding the validity of the Mortgage Contract:

– The determination of the validity of the Mortgage Contract in this case aims to recognize the obligation to perform the contract of the parties. Specifically, both the court of first instance and the court of appeal have concluded that the Mortgage Contract in this case is invalidate.

– According to Clause 1, Article 411 of the Civil Code 2005, stated that “in the event that, from the time of conclusion, the contract has an object that cannot be executed for objective reasons, then this contract shall be invalidate”. The content of this provision has also been reiterated in Clause 1, Article 408 of the Civil Code 2015. Comparing the case with the regulation, it can be seen that this case does not fall within the scope of application of this Article. When entering into the contract, Mr. C and Mrs. T’s couple, and even Bank V, did not know that the revocation of the Land use rights certificate would occur in the future. The provisions in Clauses 2 and 3, Article 411 of the Civil Code 2005 are also not compatible, as the Land use rights certificate in this case was revoked due to an error in the area. This means that the remaining land use rights after the adjustment are the assets securing the debtor’s debt repayment obligation (if the mortgage contract is determined to be valid).

It can be seen that the prerequisite condition for declaring the contract invalid in this case is that the “object cannot be performed” must appear from the time of signing the mortgage contract. However, according to the content of the case, the revocation of the Land use rights certificate occurred after the parties had entered into the Mortgage Contract, and in fact, the dispute over the mortgage of land use rights arose after the mortgage contract had been signed. Because of that, the mortgage contract still has legal validity.

Thus, it can be seen that the cassation decision of the People’s Supreme Court’s Judicial Council to not recognize the first-instance and appellate judgments when they declared the contract invalid is completely reasonable.

This is an article from TNTP on “Case law No. 36/2020/AL regarding the validity of mortgage contract for land use rights when the land use rights certificate is revoked, canceled”. We hope this article will be helpful for our dear readers.

Sincerely,

Applying temporary emergency measures while the debtor undergoes bankruptcy proceedings

In the current market economy, it is not uncommon for a business to initiate bankruptcy proceedings when they are unable to repay the debts. When a debtor falls into bankruptcy, the rights of creditors are often threatened. To protect these rights, Vietnamese law allows the application of emergency temporary measures. This article by TNTP will analyze the application of emergency temporary measures when the debtor initiates bankruptcy proceedings, to help readers better understand the mechanisms protecting the rights of the involved parties.

1. Concept of temporary emergency measures;

Emergency temporary measures are actions decided by the Court to address the urgent needs of the parties, protect evidence, and preserve assets to prevent irreparable harm or ensure the enforcement of judgments. According to the Code of Civil Procedure 2015, emergency temporary measures are applied when there are grounds to believe that failure to apply them promptly will cause irreparable harm or significant difficulties for the parties or hinder the resolution of the case.

2. Emergency temporary measures in bankruptcy proceedings

Vietnamese law stipulates several emergency temporary measures that can be applied when a debtor initiates bankruptcy proceedings. These measures are specifically outlined in Clause 1, Article 70 of the Law of Bankruptcy 2014, including:

(i) Allowing selling fragile goods, goods close to the expiration date, and goods that can hardly be bought if they are not sold on time; allowing harvesting and selling farm products or other goods and products;
(ii) Distraint and sealing assets of the entity;
(iii) Blocking the bank account of the entity;
(iv) Sealing stores and funds, keeping the accounting books and relevant documents of the entity;
(v) Prohibiting transferring the rights to the assets of the insolvent entity;
(vi) Prohibiting the change of status of the assets of the insolvent entity;
(vii) Prohibiting or forcing other relevant entities to perform some acts;
(viii) Compelling the employer to advance the salaries, wages, compensation, occupational accident and occupational disease pensions to the employees;
(ix) Other temporary emergency measures under the regulations of the law.

Each emergency temporary measure has a specific role and application suitable for each case to ensure the bankruptcy proceedings are conducted transparently, fairly, and efficiently.

3. Procedure for applying temporary emergency measures

a. Request for temporary emergency measures

• The subjects entitled to request the application of emergency temporary measures are stipulated in Clause 1, Article 70 of the Bankruptcy Law 2014, including: (i) The persons with rights and obligations who have filed for bankruptcy proceedings, which include creditors; (ii) Asset management officer; (iii) Asset management enterprise.

• The person requesting the application of emergency temporary measures must submit a written request to the competent People’s Court. The written request must include the following information: (i) Date; (ii) Name and address of the person requesting the application of temporary emergency measures; (iii) Name and address of the person to whom the temporary emergency measures are applied; (iv) Reason for applying the temporary emergency measures; (v) The temporary emergency measures to be applied and specific requirements.

Thus, creditors who have filed for bankruptcy proceedings have the right to request the Court to apply emergency temporary measures. However, the request must clearly state the reasons and the grounds proving the necessity of the emergency temporary measures.

b. Court decision

Upon receiving the request, the Court will review and decide whether to apply the emergency temporary measures. The Court’s decision must be made promptly to ensure the timely protection of the involved parties’ rights.

4. Significance of temporary emergency measures

Applying emergency temporary measures helps prevent the dissipation of assets or actions that cause damage to the debtor’s assets. This ensures that the debtor’s assets will be used to pay off the creditors.

5. Considerations

• However, it should be noted that according to Clause 1, Article 113 of the Code of Civil Procedure 2015, the persons who send the request to the Court to apply provisional emergency measures must be responsible before law for their petitions. Where the request for the application of provisional emergency measures is made improperly and causes damage to the persons against whom the temporary emergency measures are applied or to the third person, compensation must be made.

• According to Clause 1, Article 136 of the Code of Civil Procedure 2015, the person requesting the Court to apply temporary emergency measures must submit to the Courts the following guarantees: (i) A guarantee invoice secured by assets of banks or other credit institutions or other agencies, organizations or individuals; or (ii) A monetary sum, precious metals, gemstones or valuable papers as determined by the courts. However, this guarantee must be equivalent to the potential loss or damage that may arise from applying the emergency temporary measures.

The value of the guarantee is determined by the Court but must not be less than 20% of the estimated value of the assets subject to the temporary emergency measures, except when clear evidence proves that the potential loss or damage is less than 20% of the estimated asset value.

If the request for emergency temporary measures is incorrect, the requester must pay the actual costs incurred from enforcing the decision. The advance payment or guaranteed assets will be used to cover these costs.

Therefore, to ensure accurate requests from selecting the appropriate measures to providing proper grounds for the request, readers should consult legal experts or lawyers. These professionals have in-depth knowledge of bankruptcy procedures and related legal measures, thus providing detailed information and guidance on emergency temporary measures and how to appropriately and accurately establish the grounds for the request.

Legal expert consultation not only helps readers understand their rights and obligations during bankruptcy proceedings but also assists in making informed and beneficial decisions. Additionally, expert consultation helps minimize legal risks and ensures that the bankruptcy process follows the legal regulations.

This article by TNTP on “Applying temporary emergency measures while the debtor undergoes bankruptcy proceedings” aims to provide useful information to readers.

Best regards,

Legal regulations on the limitations period on mortgage contracts

The limitations period is the period during which a party has the right to file a lawsuit to request the court or arbitration to resolve a civil case to protect the infringed legal rights and interests; if this period expires, the right to sue is lost. In the article below, TNTP will present some issues related to the limitations period on a mortgage contract for the parties to refer to when initiating legal proceedings at the competent dispute settlement body.

1. On the dependency of the limitations period on a mortgage contract

Since a mortgage contract is essentially an ancillary contract, a component of the main contract – the loan contract, the filing of a lawsuit in general and the limitations period to resolve disputes, in particular, are calculated according to the limitations period of the main contract.

2. On the limitations period

According to Article 429 of the 2015 Civil Code, the limitations period to request the court to resolve contract disputes in general, and mortgage contract disputes in particular, is 03 years from the date the entitled person knew or should have known that their legal rights and interests were infringed. However, the reclamation of assets in a loan contract does not apply to the limitations period because it falls under the category of “requesting the protection of ownership rights.” The lender no longer owns the loaned asset from the moment the borrower receives it according to the following regulation: “A borrower shall become the owner of borrowed property from the time of delivery of the property.” Therefore, when the lender sues to require the borrower to fulfil the payment obligation, the principal debt amount is not subject to the limitations period, but the limitations period applies to the interest debt and other related costs arising from the loan contract.

The 2015 Civil Code stipulates “limitations period to request the court to resolve contract disputes”, but does not mention arbitration. Meanwhile, the 2015 Civil Code stipulates “If a particular civil right is violated or is under a dispute, the protection of such right shall be implemented as prescribed in procedural law at the court or arbitration.” According to Article 33 of the 2010 Law on Commercial Arbitration, except for other provisions in specialized laws, the limitations period under arbitration procedures is 02 years from the time the legal rights and interests are infringed.

3. On the periods excluded from the limitations period

The 2015 Civil Code stipulates periods excluded from prescriptive periods for initiating legal action for civil cases and from prescriptive periods for requesting resolution of civil cases, including:

• The period during which a force majeure event or an objective obstacle occurs, preventing the entitled person from filing a lawsuit or making a request within the limitations period.

• The period during which there is no representative in cases where the entitled person is a minor, has lost civil act capacity, has difficulty in perception and behaviour control, or has limited civil act capacity. The minor, a person who has lost civil act capacity, a person with difficulty in perception and behaviour control, or a person with limited civil act capacity does not have another representative to replace in the following cases: the representative dies if an individual, or ceases to exist if a legal entity; the representative, for legitimate reasons, cannot continue to represent.

4. On the re-commencement of the limitations period

When the limitations period expires, the limitations period starts can re-commence in the following cases:

• The obligated party has acknowledged part or all of their obligation to the claimant;

• The obligated party acknowledges or fulfils part of their obligation to the claimant;

• The parties have reconciled.

5. On the acceptance of cases of the Court

Previously, the court would not accept or would return the case if the limitations period had expired. However, according to the 2015 Civil Procedure Code, in case the limitations period expires, the court still has to accept the case and only applies the limitations period rules upon the request of at least one party.

The above is the article by TNTP on “Legal regulations on the limitations period on mortgage contracts”. If you have any issues to discuss, please contact TNTP for timely support.

Best regards,

The steps for debt recovery in the field of construction

To complete a construction project, businesses need to ensure a large, stable and long-term capital. However, during project implementation, many problems arise that can affect capital flows, the most basic of which can be anticipated is the rising debts. The question is, how business can recover the debt and ensure the stability of capital flow during construction? In the following article, TNTP’s lawyer will give our opinion on: “The steps for debt recovery in the field of construction”.

1. Identify the debts that need priority for recovery

In the activities of businesses in the field of construction in particular and in other fields in general, many different debts can arise. Some debts may not have a big impact on the financial flow, but others may have a huge impact on the financial capacity of the business.

Therefore, the first step in debt collection is that businesses need to quickly recover the debt that may greatly affect business operations to eliminate potential financial risks. According to our experience, a business debt that needs priority for recovery has the following characteristics:

– The Debts incurred for more than 12 months
– The debtor has unstable business operations
– Large debt value (over 50% of the value of the construction project)
– The debtor shows signs of not cooperating with payment

Accordingly, after identifying priority debts for recovery, businesses need to prepare for the next step which is debt reconciliation.

2. Debt reconciliation

Debt reconciliation is when the business and the debtor agree to determine the exact value of the debt and the debtor acknowledges the obligation to repay. This is a very important step for later stages of debt collection, because when the debtor does not acknowledge the debt, the business will have to prove that they have the right to recover the debt, as well as prove the value of the debt. As a result, debt collection will become a dispute resolution job that costs a lot of time and effort as well as expenses of the business.

Debt reconciliation should be performed continuously from the time the debt begins to arise to limit the possibility of the debtor refusing the debt when the value becomes large. We believe that businesses should process the Debt reconciliation monthly or quarterly to best ensure their rights and create favorable conditions for the debt collection process if any arises later.

3. Negotiate phase

As the first step in the debt collection process, the business will remind the debtor to pay the debt by negotiating on the basis of goodwill, respect and cooperation. This is the stage when the business explores whether the debtor is willing to pay the debt or not, so the implementation process needs to limit unnecessary pressure.

If the negotiation goes well, businesses can save significant costs and time to collect debt, so at this stage businesses can consider “Win-Win” options to increase the likelihood of successful debt recovery if the debtor also shows their willingness to pay and have the ability to pay the debt.

In cases where the businesses have tried to negotiate in good faith, but the debtor does not cooperate to pay the debt, the businesses should consider proceeding with the proceedings at a competent dispute resolution agency.

4. Conduct the litigation phase

When negotiation does not show any good sides, the business can consider taking legal action. According to the provisions of law, litigation is the process and procedure for resolving disputes arising in a legal relationship, then the dispute resolution body will have the authority to conduct proceedings including but not limited to: Courts and Arbitration Center.

When conducting the litigation stage to collect debt, the business will submit a Petition to the dispute resolution body, namely the Court and the Arbitration Center based on the choices of the parties in the Contract. The dispute resolution body will review the Petition and accompanying evidence of the business to issue a legally effective Decision/Judgment/Award if the Petition and these documents have sufficient grounds for the business’s lawsuit claim.

After the dispute resolution body issues a legally effective Decision/Judgment/Award forcing the debtor to pay the debt, the business can proceed with the Judgment Enforcement stage so that the competent Judgment Enforcement authorities take necessary measures on behalf of state power to force the debtor to pay the debt to the businesses in accordance with the Decision/Judgment/Award that has legal effect.

Above is an article by lawyer TNTP on the topic: “The steps for debt recovery in the field of construction“. Hopefully, this article brings value to readers.

Best regards,

Invalid civil contracts and legal consequences of invalid civil contracts

Invalid civil contracts and the legal consequences of invalid civil contracts are important topics in contract law. An invalid civil contract is a civil transaction that expresses the will of the participating parties but violates the conditions for the contract’s validity as stipulated in the Civil Code. In the following article, TNTP will present the basic information you need to know about invalid civil contracts and the legal consequences of invalid civil contracts.

1. Recognizing invalid civil contracts

Article 122 of the 2015 Civil Code stipulates: “Civil transactions which fail to satisfy any one of the conditions specified in Article 117 of this Code shall be invalid.”. Additionally, Clause 1, Article 407 of the 2015 Civil Code states, “The provisions on invalid civil transactions in Articles 123 to 138 inclusive of this Code shall also govern invalid contracts.”. Therefore, a contract that fails to satisfy the requisite legal conditions for validity as prescribed by law, or in cases where the law stipulates otherwise, is considered an invalid civil contract.

Cases of invalid civil contracts include the following:

• Invalid contracts due to failure to meet validity conditions, specifically:

 The purpose and content of the contract breach of legal prohibitions or contravention of social ethics;

 The parties entering into the contract were deceived, threatened, or coerced;

 The contract was established fraudulently;

 The parties establishing and executing the contract are minors or legally incapacitated persons or persons with limited cognition and behaviour control or persons with limited legal capacity;

 The parties entered into the contract due to a misunderstanding;

 The parties entered into the contract at a time when they were lacking in cognition and behaviour control;

 The contract does not comply with the required form.

However, the 2015 Civil Code also stipulates that in certain cases, even if a civil contract is established under the aforementioned conditions of invalidity, the contract may still be valid. For example, if the contract has been established as required to be in writing but the document does not comply with the stipulations of the law, and one or both parties have already performed at least two-thirds of their obligations in the transaction, then upon the request of one or both parties, the court may issue a decision recognizing the validity of that transaction.

• Invalidity of civil contracts due to the impossibility of performing subject

If at the time of entering into the contract, the contract has a subject that cannot be performed, then this contract is invalid. This provision applies in cases where the contract has one or more parts of the subject that cannot be performed, but the remaining parts of the contract are still valid.

• Invalidity of civil contracts due to the invalidity of principal contract

The invalidity of the principal contract results in the termination of the ancillary contract, unless the parties agree that the ancillary contract replaces the main contract. This provision does not apply to types of security for the performance of obligations. The invalidity of the ancillary contract does not terminate the principal contract unless the parties agree that the ancillary contract is an inseparable part of the principal contract.

• Invalidity of the civil contract according to the specific provisions

In addition to the 2015 Civil Code, which specifies cases of contract invalidity, specialized laws also have their provisions regarding the invalidity of contracts. The contract will be governed by the relevant specialized law, which will be applied to resolve the declaration of invalidity of the contract and the legal consequences resulting from its invalidity.

2. Legak consequences of invalid civil contracts

The legal consequences of an invalid contract are carried out according to the provisions of Article 131 of the 2015 Civil Code. Accordingly, an invalid contract will lead to the following legal consequences:

• An invalid civil transaction shall not give rise to, change or terminate any civil rights and obligations of the parties as from the time the transaction is entered into.

If a civil contract is legally entered into, it becomes effective in practice. In the case of an invalid civil contract, if the parties have not yet performed the contract, they are not required to continue its execution. If the parties are currently performing the contract, they must stop its execution.

• In case a civil transaction is invalid, the parties shall restore everything to its original state and shall return to each other what they have received; If the restitution can not be made in kind, it may paid in money

This consequence is stipulated in Clause 2 of Article 131 of the 2015 Civil Code; however, this provision has limitations as it cannot be applied to contracts whose subject is acts. Unlike with property, where parties in a contract can return the property to each other, in the case of contracts whose subject is acts, the parties cannot return the acts to each other.

• A bona fide person receiving yield and/or income is not required to return such yield and/or income

During the period from when the party receiving the asset transfers the asset until the contract is declared invalid, a bona fide person has the right to own the yield and income arising from the asset, which is the subject of the invalid contract.

• The party at fault which caused the damage must compensate

A party is considered at fault if this party acts in a way that leads the other party to mistakenly believe that this party has all the necessary conditions to enter into the contract. In cases where both parties are at fault, determining the degree of fault of each party is the basis for specifying the extent of compensation.

Above is the article “Invalid civil contracts and legal consequences of invalid civil contracts” that TNTP presents to you. If you have any issues that need discussion, please contact TNTP for timely assistance.

Best regards,

Why does the business not want to settle overdue debts with its partners?

Incurring debt in business activities is normal for businesses. However, for many different reasons, debtors often want to extend the debt to get the greatest benefit. In this article, TNTP’s lawyer will give an opinion on the reasons why the business does not want to settle overdue debts with its partners.

1. The debt is unclear and disputes are likely to arise

The most important thing in the debt collection process is to accurately determine the amount of debt that needs to be recovered. When the debt amount has not been clearly identified by the parties, it will be a reasonable reason for the debtor not to make payment. The debt amount needs to be determined specifically and in detail by the parties in the contract and must be expressed in specific documents such as invoices, payment requests, and most importantly the debt reconciliation records to show consensus in determining the final amount of the debt.

In TNTP’s opinion, the debtor’s unwillingness to pay when the parties have not agreed on the value of the debt is common and is also a fair reason that creditors need to pay attention to. Although the creditor is the party with the right to request payment, it needs to be expressed clearly and with grounds to avoid abusing his or her rights to force the debtor to pay the amount that exceeds the amount of the debt.

The fact that the debt amount is not clearly determined by the parties can cause a debt recovery case to become a business dispute. At that time, other issues related to the contract can also become the subject of disputes such as the delivery of goods, issuance of invoices, and the performance of the parties in accordance with the agreement and the law. This will cause many other complicated problems in debt collection, affecting the quality of debt collection and even the business operations of the enterprise.

2. The debtor tries to appropriate capital

Many businesses with weak financial capacity have temporarily used amounts payable to creditors for their business activities, or they have temporarily used the value of a debt to “set-off” other debt with higher priority and continue to delay payment for as long as possible to continue to rotate capital. When a business can prolong debt payment, it will appropriate a lot of capital with lower interest rates than mobilizing capital through banks.

This is one of the main reasons why many businesses, despite having the condition and ability to pay but not repay their debt, because compared to completely paying off the debt, the longer the appropriation of capital will help the business maintain its viability and maintain a stable amount of capital with little disturbance. In addition, appropriation of capital can also be considered a form of unfair competition when the debtor’s failure to repay the debt on time will cause creditors to lose their capital to carry out business activities. Especially, the debts with large amount may cause the creditor to fail to achieve its business goals, affecting the creditor’s operation.

Therefore, as soon as it is determined that the debtor has appropriated capital, the creditor needs to quickly implement necessary debt recovery to protect both their rights and their capital.

3. The debtor has low revenue or is no longer able to operate

There are many reasons why debtors with low revenue are no longer able to pay, such as bad business decisions, market difficulties, or changes in the law. This is a situation that no creditor wants to happen to their debtors, but in reality, most of the difficult-to-recover debts on the market belong to the group of debtors that are no longer able to pay and are no longer operating. When the debtor is no longer able to operate or make a profit, paying off the debt becomes almost impossible.

The only solution for creditors is to regularly check and collect debts as soon as possible before the debtors fall into a “dying state”. The debtor’s insolvency status will likely put an end to all debt collection efforts.

Above is an article by lawyer TNTP on the topic: ” Why does the business not want to settle overdue debts with its partners?” Hopefully, this article brings value to readers.

Best regards,

TNTP & ASSOCIATES INTERNATIONAL LAW FIRM

  • Office in Ho Chi Minh City:
    Room no. 1901, 19 th Floor Saigon Trade Center Tower, No. 37 Ton Duc Thang Street, Ben Nghe Ward, District 1, Ho Chi Minh City
  • Office in Hanoi City:
    No. 2, Alley 308 Tay Son str, Thinh Quang Ward, Dong Da Dist, Hanoi City
  • Email: ha.nguyen@tntplaw.com


    The copyright belongs to: TNTP & Associates International Law Firm