Skip to main content

What Contractors Should Do When Investors Delay Payment in Vietnam

When an investor (project owner) in Vietnam pays late, a contractor should first identify why payment is delayed, then negotiate in writing and obtain a written confirmation of the debt. If negotiation fails, the contractor sends a formal payment demand claiming late payment interest and damages, and may then bring a claim before Commercial Arbitration or the competent People’s Court, as agreed in the contract.

Late payment by the investor is a common risk in construction. It strains the contractor’s cash flow and solvency, leaves wages, materials and loan interest unpaid, disrupts construction progress and can affect the quality of the project. This article sets out the common causes of payment delays and the measures contractors should take at each stage: before a delay arises, when it occurs, and when legal action becomes necessary.

Why investors delay payment

Before applying any measure, the contractor needs to establish the actual cause of the investor’s failure to pay on time. Not every delay is intentional. A correct diagnosis lets the contractor choose a suitable recovery strategy and avoid measures that could harm the prospects of recovery or the ongoing contractual relationship.

Common causes include:

  • Cash flow imbalance: the investor has difficulty raising capital, faces problems with disbursement from credit institutions, or lacks investment funds.
  • Administrative procedures: acceptance records, volume approvals, and payment or final settlement dossiers must pass through several departments for verification, so disbursement takes longer than expected. The project’s final settlement may also be incomplete.
  • Unsigned or unapproved documents: acceptance records or payment documents have not been fully signed or approved.
  • Disputes over volume or quality: the investor claims that the contractor miscalculated the completed volume, did not build in line with the design dossier, or refuses acceptance because the quality is unsatisfactory.
  • Withholding and set-off: the investor withholds payment for warranty obligations, or sets off penalties, liquidated damages or other amounts it considers due under the contract.
  • Deliberate delay: the investor intentionally postpones payments due under the agreed milestones or for completed work.

The tactics investors use to postpone payment, and how to counter each one, are analysed in our article on common strategies investors use to delay debt payments.

Step 1: Reduce the risk before any delay arises

Draft clear payment and remedy clauses

From the negotiation and signing stage, the contractor should clearly set out the payment terms: the payment schedule, payment method and value of each stage. The contract should also specify the consequences of late payment, such as penalties for breach, late payment interest and compensation for damages.

The right to suspend construction when the investor breaches its payment obligation should also be expressly recorded. This clause is an important legal basis during contract performance.

To secure payment, contractors should consider security measures such as payment guarantees or retention of title over materials and equipment. The dispute resolution clause should be reviewed carefully before signing, so that any dispute can be resolved effectively. Whether a guarantee clause actually helps the contractor collect is discussed in payment guarantee clauses in construction contracts.

Work in stages and keep written records

  • Divide contract performance into several stages, with acceptance, work confirmation and interim or final account settlement at the end of each stage. This reduces the risk of a large outstanding debt and improves recovery at each stage.
  • Send every request relating to acceptance or payment in writing. Written requests create clear evidence and protect the contractor if a dispute arises.
  • Keep all records of completed work, including acceptance and handover records and documents confirming volumes. These are used to compare against, and prove, the investor’s payment obligation.
  • Keep evidence that each request was submitted, including proof that the investor received the documents or acknowledged its payment obligation.
  • Set a timeline for each step of recovery: submission of requests, reminders, negotiation and initiation of legal proceedings. This creates pressure on the investor, prevents delays from continuing indefinitely and allows the contractor to escalate when necessary.

Step 2: Negotiate and document when payment is late

When late payment arises, the contractor should first negotiate in good faith to preserve cooperation and find a workable solution. Negotiation is more effective when it is structured as follows.

Separate undisputed amounts from disputed amounts

Demanding the entire outstanding debt in a single payment is often impracticable. It may be rejected or lead to a prolonged dispute, particularly where some payment items are contested. Contractors should classify the debt into two groups:

  • Amounts for completed works that meet the payment conditions and have clear contractual and legal grounds. These have a high likelihood of recovery and should be pursued first, to improve cash flow, relieve financial pressure and create a basis for the remaining items.
  • Disputed amounts relating to quantities, unit rates, or variations and additional works outside the scope of the contract. These usually take longer to verify. They should be identified separately for negotiation, reconciliation and step-by-step completion of supporting documents, and not mixed with debts already due.

For the disputed group, the contractor should prepare meeting minutes, formally record outstanding issues and set a roadmap for resolution. During negotiation, the contractor may also ask the investor for partial payments to maintain operating cash flow and reduce the risk of bad debt.

Respond to the reason the investor gives

Investor’s reason Contractor’s response
No formal acceptance yet Issue a written request proposing a reasonable timeline for organising and completing the acceptance procedures.
Refusal or delay in signing final account statements or as-built documents Send formal correspondence consistently and record each delay. This creates pressure and clarifies the responsibilities of the parties.
Reduced quantities or adjusted unit prices Review the contract and all documents signed between the parties. Prepare a written record of the change, stating which party requested it and whether it was approved, and request the documents evidencing that approval.
Additional works without a signed contract addendum Obtain partial acceptance minutes, handover records or records confirming completed quantities. Collect factual evidence such as emails, messages and site photographs.
Set-off against penalties or damages Check whether the penalties or damages comply with the law and the parties’ agreements, and request clear supporting evidence.
Financial difficulties Negotiate a specific payment schedule with clear commitments, to limit the risk of prolonged delay.

Where the investor will not sign acceptance minutes, see whether acceptance minutes without the investor’s signature are legally valid.

Obtain a written confirmation of the debt

The contractor should ask the investor to confirm the debt in writing. The confirmation should state the total amount owed and the payment deadline, and bear the signature of the authorised representative and the company seal.

This document is the basis for further negotiation. It is also legally binding evidence of the payment obligation if the dispute is later resolved by a court or arbitration.

Consider suspending construction

If the delay is prolonged and causes serious damage, the contractor may consider suspending construction. This is only possible where there is a clear legal basis in the contract or under the law, and the notice procedure is strictly followed. The contract terms must be assessed carefully, so that the contractor is not itself found to be in breach.

Before suspending, the contractor must send the investor an official written notice stating the reason, the legal grounds, the effective date of the suspension and the conditions for resuming construction.

Step 3: Take legal measures to recover payment

When negotiation fails, the contractor can take legal measures to protect its rights.

Send a formal payment demand

The contractor first sends an official payment demand, together with a claim for late payment interest and compensation for damages, if any. Late payment interest, penalties or compensation may be claimed if they are agreed in the contract or provided for by applicable law, so the relevant contract provisions, related agreements and applicable law must be checked.

For a compensation claim, the contractor must prove the actual damage and its causal link to the investor’s late payment. If the damage results from a force majeure event, or is entirely the contractor’s fault, the investor may be exempt from liability to compensate.

Reclaim supplied materials and equipment

Where the contract provides for, or the parties have agreed on, retention of title over materials and equipment, the contractor may seek to reclaim those assets if the investor breaches its payment obligation. The legal conditions under applicable law and the contract terms must be reviewed carefully first.

Bring a claim before arbitration or the court

If the investor still does not pay, the contractor may file a claim with Commercial Arbitration or the competent People’s Court, as agreed by the parties. Particular attention must be paid to documents, evidence and compliance with procedural requirements, as these determine whether the claim is accepted.

Signed acceptance documents are not the only evidence. Where acceptance documents are not fully signed by all parties, the contractor may still recover the debt if it can show completion of the works through other evidence, such as final account documents, debt reconciliation statements, handover records, emails, messages, or documents and photographs of the works actually performed.

When to escalate and engage legal counsel

The move from negotiation to litigation typically comes when the investor no longer shows willingness to cooperate, or when there are clear signs of payment risk or inability to pay. Warning signs include:

  • acceptance records, as-built documents, final account documents or debt reconciliation statements remain unsigned for an extended period;
  • the investor begins to deny its payment obligation or disputes the completed scope of work;
  • the investor avoids communication, changes its address or becomes difficult to contact;
  • the investor deliberately delays or prolongs payment.

At this point, the contractor should promptly adopt appropriate legal measures and may engage legal counsel. Lawyers can:

  • review the contract and determine the legal basis for the payment claim;
  • formulate clear, well-founded claims and build a complete set of supporting documents;
  • prepare the claim file and calculate late payment interest and damages incurred;
  • represent the contractor in negotiations with the investor and in court or arbitration proceedings.

For foreign contractors, the right partner in Vietnam is a law firm rather than a collection agency, because debt collection services are a prohibited business line in Vietnam. TNTP’s construction debt recovery lawyers can assess the file and advise on negotiation, arbitration or litigation against the investor.

Common mistakes that weaken recovery

Many contractors struggle to recover from investors not because they lack a legal basis, but because of mistakes in handling the debt:

  • communicating only by phone calls or messages, without formal written records, so there is no clear evidence when it is needed;
  • waiting for completion and final settlement of the whole project before requesting a single lump-sum payment, losing the chance to recover at each stage;
  • combining disputed receivables with receivables already due, which delays recovery of the undisputed amounts;
  • allowing payment delays to continue for too long without escalating to stronger measures.

Contractor checklist when the investor pays late

  1. Identify the real cause of the delay.
  2. Gather the contract, acceptance and handover records, volume confirmations and proof that payment requests were received.
  3. Split the debt into amounts already due and disputed amounts; pursue the first group immediately.
  4. Answer the investor’s stated reason in writing and record every delay.
  5. Obtain a written debt confirmation signed by the authorised representative and sealed.
  6. Suspend construction only with a contractual or legal basis and after official written notice.
  7. Send a formal payment demand claiming late payment interest and damages.
  8. If payment still does not follow, file a claim with Commercial Arbitration or the competent People’s Court, as agreed in the contract.

Late payment by the investor is a foreseeable risk in construction. With well-drafted contracts, careful document management and timely use of negotiation and legal measures, contractors can protect their rights and keep their finances stable during the project. For a wider view of contractor remedies, see our guide to construction debt and late payment in Vietnam. Contractors that need case-specific advice can contact TNTP’s debt recovery and dispute resolution team.

TNTP & ASSOCIATES INTERNATIONAL LAW FIRM

  • Office in Ho Chi Minh City:
    Room no. 1901, 19 th Floor Saigon Trade Center Tower, No. 37 Ton Duc Thang Street, Saigon Ward, Ho Chi Minh City
  • Office in Hanoi City:
    No. 2, Alley 308, Tay Son Street, Dong Da Ward, Hanoi City

The copyright belongs to: TNTP & Associates International Law Firm